List of Action Items

List created on 2012- 6-30 20:15:45 -0700

Action Item ID03-T4-1: Douglas Cripe will investigate whether additional options can be made available for the status of a Task activity in the Task Sheet. The new options should include 'suspended'. Responsible: Douglas Cripe, Deadline: 2012-06-30.

Action Item ID03-T4-2: All Task Team members will provide their personal prioritization of Task Activities to Hans-Peter Plag, who will prepare an aggregated overview over the prioritizations. Responsible: All, Deadline: 2012-06-30.

Status of Action Item ID03-T4-2: Open.
Report: No prioritizations were received. Reported on 2012-06-30 by Hans-Peter Plag.

Action Item ID03-T4-3: Hans-Peter Plag will check to what extent the individual ideas presented at the WPS concerning user engagement and the role of the CoPs were analysed and included in the WPS report. He will report back to the Task Team. Responsible: Hans-Peter Plag, Deadline: 2012-06-30.

Status of Action Item ID03-T4-3: Done.
Report: The Draft report of the WP Symposium summarizes the main recommendations made and points raised for these topics. For details, see the Draft Report . Reported on 2012-06-30 by Hans-Peter Plag.

Action Item ID03-T4-4: Hans-Peter Plag will distribute the extended abstract on the G-STSS to the Task team. Responsible: Hans-Peter Plag, Deadline: 2012-06-10.

Status of Action Item ID03-T4-4: Done.
Report: Hans-Peter Plag distribute the extended abstract to the Task Team members. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-1: Ian McCallum will prepare a draft description of the Best Practice in data citation and distribute it to the Task team for comments. Responsible: Ian McCallum, Deadline: 2012-05-31.

Status of Action Item ID03-M1-1: Open.
Report: This AI is delayed due to other commitments. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-2: Ian McCallum will prepare a draft text on data citation for the GEOSS Web Portal and distribute it to the Task team for comments. Responsible: Ian McCallum, Deadline: 2012-05-31.

Status of Action Item ID03-M1-2: Open.
Report: This AI is delayed due to other commitments. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-3: Hans-Peter Plag will discuss with the GCI Provider group how the Data Citation can be implemented in the GCI. Responsible: Hans-Peter Plag, Deadline: 2012-05-31.

Status of Action Item ID03-M1-3: Open.
Report: Hans-Peter Plag discussed the implementation of the data citation guidelines with the GCI Provider group. The group is now waiting for more input, including a text for the GEOSS Web Portal. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-4: Ian McCallum and Hans-Peter Plag will prepare Version 2 of the Data Citation Standard and address the issues identified by ICSU-CODATA. Responsible: Ian McCallum, Hans-Peter Plag, Deadline: 2012-06-30.

Action Item ID03-M1-5: Hans-Peter Plag will prepare a draft GEO label concept and implementation plan and distribute it to the Task team for discussion. Responsible: Hans-Peter Plag, Deadline: 2012-05-31.

Status of Action Item ID03-M1-5: Open.
Report: This AI is delayed due to other commitments. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-6: Hans-Peter Plag will initiate a discussion with the GCI Provider Group on GEO Label implementation. Responsible: Hans-Peter Plag, Deadline: 2012-05-31.

Status of Action Item ID03-M1-6: Open.
Report: Hans-Peter Plag raised the issue of a GEO Label with the GCI provider group and the group is now waiting for a concept to be submitted to them for consideration. Reported on 2012-06-04 by Hans-Peter Plag.

Action Item ID03-M1-7: Ian McCallum will make an effort to solicit additional compelling examples for the GEOSS Portfolio from the EGIDA Project. Responsible: Ian McCallum, Deadline: 2012-05-31.

Status of Action Item ID03-M1-7: Open.
Report: A new proposal was submitted and has been distributed to three reviewers. More proposals are still needed.\EOB

Reported on 2012-06-30 by Hans-Peter Plag.

Action Item ID03-M1-8: Hans-Peter Plag will write to all SB Task leads and ask for considerations to submit proposals for compelling examples to ID-03. Responsible: Hans-Peter Plag, Deadline: 2012-05-31.

Status of Action Item ID03-M1-8: Open.
Report: A new proposal was submitted and has been distributed to three reviewers. More proposals are still needed.\EOB

Reported on 2012-06-30 by Hans-Peter Plag.

Action Item ID03-T3-2: Bente Lilja Bye and Joan Maso will prepare the next version of the GEO Label white paper document and distribute it to the Task team. Responsible: Bente Lilja Bye, Joan Maso, Deadline: 2012-04-21.

Status of Action Item ID03-T3-2: Open.
Report: Bente Lilja Bye will discuss with Joan Maso how to approach this AI. Reported on 2012-06-04 by Hans-Peter Plag.