Fifth Telecon of the Task Team of GEO Task ID-03
Telecon
July 2, 2012, 13:00 - 14:00 UTC
Minutes (Version 0.1 of 2012- 7-30 5:12)
Participants:
Hans-Peter Plag,
NBMG, University of Nevada, Reno
(Task Co-Lead (IEEE) and Point of Contact)
Douglas Cripe,
GEO Secretariat
(Contributor, GEO Sec.)
Ian McCallum,
IIASA
(Co-Lead, EGIDA Project and EC)
Anna Riverola,
Universitat Autònoma de Barcelona
(Contributor, GeoViqua)
Massimo Menenti,
CEOP-AEGIS
(Co-Lead, EC, CEOP-AEGIS)
Agenda:
1
Acceptance of the Agenda, Minutes of T4, Action Items
2
Reports from Task Team members
3
ID-03 and Strategic Targets
A report on the relation of ID-03 and the GEOSS Strategic Targets has been prepared
for the ID-IB, which used the report for a report to the ExCom. The URR has been
used to visualize the links between ID-03 and the Targets. This revealed that
most "to be achieved through" bullets of the Science and Technology Strategic Target
are not addressed by ID-03. See
the report
and the
draft ID-IB
methodology
.
4
The GEOSS Science and Technology Service Suite (GSTSS)
An initial page for the GSTSS has been established at
http://www.gstss.org
.
The menu will be discussed.
For a description of the GSTSS, see the
abstract
for ICHMET.
5
Any other business
6
Date and Time of the next ID-03 Monthly Telecon
It is proposed to organize the next ID-03 telecon on August 6, 2012.
7
Summary of Action Items
Notes:
1
Acceptance of the Agenda, Minutes of T4, Action Items
Hans-Peter Plag
opened the meeting. The agenda was accepted as proposed. There were no comments on the minutes of T4.
The Action Items were briefly reviewed. Concerning
Action Item
ID03-T4-1:
Douglas Cripe
will investigate whether additional options can be made available for the status of a Task activity
in the Task Sheet. The new options should include 'suspended'.
Responsible:
Douglas Cripe,
Deadline:
2012-06-30,
Douglas Cripe
reported that these additional option can be implemente
Hans-Peter Plag
reported that noone followed up
Action Item
ID03-T4-2:
All Task Team members will provide their personal prioritization of Task Activities to
Hans-Peter Plag,
who will prepare
an aggregated overview over the prioritizations.
Responsible:
All,
Deadline:
2012-06-30.
Ian McCallum
stated that work related to
Action Item
ID03-M1-1:
Ian McCallum
will prepare a draft description of the Best Practice in data citation and distribute it to the Task team
for comments.
Responsible:
Ian McCallum,
Deadline:
2012-05-31,
Action Item
ID03-M1-2:
Ian McCallum
will prepare a draft text on data citation for the GEOSS Web Portal and distribute it to the Task team
for comments.
Responsible:
Ian McCallum,
Deadline:
2012-05-31,
Action Item
ID03-M1-4:
Ian McCallum
and
Hans-Peter Plag
will prepare Version 2 of the Data Citation Standard and address the issues identified
by ICSU-CODATA.
Responsible:
Ian McCallum,
Hans-Peter Plag,
Deadline:
2012-06-30,
was delayed but would be
followed up in the next weeks. Similarly,
Hans-Peter Plag
reported a delay for
Action Item
ID03-M1-5:
Hans-Peter Plag
will prepare a draft GEO label concept and implementation plan and distribute it to the
Task team for discussion.
Responsible:
Hans-Peter Plag,
Deadline:
2012-05-31.
Concerning
Action Item
ID03-M1-8:
Hans-Peter Plag
will write to all SB Task leads and ask for considerations to submit proposals for
compelling examples to ID-03.
Responsible:
Hans-Peter Plag,
Deadline:
2012-05-31,
Hans-Peter Plag
mentioned that a new proposal had been submitted but emphasized that more proposals were
needed.
2
Reports from Task Team members
No additional reports were made.
3
ID-03 and Strategic Targets
A brief report on the relation of ID-03 and the GEOSS Strategic Targets had been prepared
for the ID-IB, which was included in the report if the ID-IB to the ExCom. The URR has been
used to visualize the links between ID-03 and the Targets. This revealed that
most "to be achieved through" bullets of the Science and Technology Strategic Target
are not addressed by ID-03. See
the report
and the
draft ID-IB
methodology
.
After some discussion, it was concluded that the science review of the GEO Work Plan was
an important activity. This resulted in:
Action Item
ID03-T5-1:
Hans-Peter Plag
will ask the ID-IB about options concerning a science review of the GEO Work Plan.
Responsible:
Hans-Peter Plag,
Deadline:
2012-09-10.
4
The GEOSS Science and Technology Service Suite (GSTSS)
Hans-Peter Plag
introduced the GSTSS and mentioned that an initial page for the GSTSS has been
established at
http://www.gstss.org
.
The menu was briefly discussed.
A description of the GSTSS is given in the
abstract
for ICHMET. After a breif discussion,
the following AIs were agreed:
Action Item
ID03-T5-2:
All will send comments to
Hans-Peter Plag
on the initial web page for the GSTSS
available at
http://www.gstss.org
Responsible:
All,
Deadline:
2012-08-01.
Action Item
ID03-T5-3:
Douglas Cripe
will talk to Rick in the GEO Sec about the GSTSS.
Responsible:
Douglas Cripe,
Deadline:
2012-08-01.
5
Any other business
Douglas Cripe
reported that the transition to the new director of the GEO Secretariat is going well.
6
Date and Time of the next ID-03 Monthly Telecon
It was agreed to hold the next ID-03 telecon on August 6, 2012.
7
Summary of Action Items
Action Item
ID03-T5-1:
Hans-Peter Plag
will ask the ID-IB about options concerning a science review of the GEO Work Plan.
Responsible:
Hans-Peter Plag,
Deadline:
2012-09-10.
Action Item
ID03-T5-2:
All will send comments to
Hans-Peter Plag
on the initial web page for the GSTSS
available at
http://www.gstss.org
Responsible:
All,
Deadline:
2012-08-01.
Action Item
ID03-T5-3:
Douglas Cripe
will talk to Rick in the GEO Sec about the GSTSS.
Responsible:
Douglas Cripe,
Deadline:
2012-08-01.
Minutes prepared by
Hans-Peter Plag
|